YA Group was engaged to provide surety consulting and engineering expertise following a contractor default and performance bond claim on a municipal water tank rehabilitation project. The project involved repairs and protective coating restoration for two municipal water storage tanks, requiring careful coordination to maintain uninterrupted water service while supporting the surety through the completion process. By combining technical expertise with practical project management, YA helped position the project for a timely and cost-effective resolution.
Challenge Overview
When YA became involved, work had progressed unevenly across the two tanks. One structure was only partially repaired, while the second had undergone surface preparation but had not yet advanced into the repair phase. Because the tanks served an active municipal water system, repairs could not occur simultaneously without affecting the owner’s operations.
In addition to coordinating the technical scope of work, the project required an expedited path forward to minimize schedule impacts, support the performance bond claim process, and reduce the potential for additional project costs.
YA Group’s Area of Impact
YA’s surety consultants quickly evaluated the project status and developed a strategy to complete the remaining work while maintaining continuous water service throughout construction. Leveraging extensive experience with municipal infrastructure projects, the team established a practical sequencing plan that allowed repairs to proceed efficiently without disrupting operations.
YA also supported the re-procurement process by preparing bid packages and coordinating with qualified specialty contractors capable of completing the highly specialized repair and coating work. Throughout the project, YA provided technical guidance to support the takeover process, assisted with project coordination, and worked closely with the completion contractor through final acceptance.
By combining engineering expertise with practical surety consulting, YA helped expedite project completion, minimize delays, and support a successful outcome for all stakeholders. The collaborative approach reduced the overall financial impact of the contractor default, while allowing the municipality to maintain essential public infrastructure throughout the repair process.